| Week ending |
Progress report |
13 October (wk 17) |
Electrical work completed, audio system installed, decorating finished. First services held in re-furbished surroundings. |
 |
6 October (wk 16) |
Carpets laid, pews returned and polished, communion rail completed and cross hung. Site barriers removed, planting beds prepared, car park cleared and cleaned. |
 |
29 September (wk 15) |
Further electrical and joinery work done. Main floor sanded and re-sealed. External painting completed. Organ unwrapped and re-tuned. |
 |
22 September (wk 14) |
Balustrade and handrails fitted outside. Further electrical and decorating work done inside. Communion rail constructed. Fittings installed for the lighting bar. |
 |
15 September (wk 13) |
New front door hung, all doors and panels glazed. A good part of the internal decorating completed. |
 |
8 September (wk 12) |
Radiators re-fitted, doors hung, and gallery rail constructed and installed. Decorating begun. |
 |
1 September (wk 11) |
Plastering done in the new porch. Oak door frames delivered and fitting begun. Audio-visual cabling laid. |
 |
25 August (wk 10) |
Gallery wall constructed. Electrical cables laid. Re-glazing completed and refurbished opening lights re-installed. Surplus furniture removed and front furniture re-polished. |
 |
18 August (wk 9) |
All slabs now laid for the new entrance. Staircase fitted to the gallery. Gallery floor boarded. |
 |
11 August (wk 8) |
Further slabs laid outside. Joists fitted for the gallery floor. New flooring added in the communion area. |
 |
4 August (wk 7) |
Coping stones added to the external dwarf wall. Surface slabs laid on the new ramp. |
 |
28 July (wk 6) |
Framework for the new porch erected. Furniture dismantled and removed from the front of the church. Work begun on the new central steps at the main entrance. |
 |
21 July (wk 5) |
Further work done on the ramp. Preparations made for re-positioned central steps. Church porch dismantled. Foundations dug for new porch wall. |
 |
14 July (wk 4) |
Church pews removed for storage. Cabling and plumbing stripped inside ready for the taking down of the porch. Dwarf wall built outside. |
 |
7 July (wk 3) |
Builders, Redfern & Strickland, arrive on site. Work begins on the main entrance. Foundations dug for the dwarf wall that will surround the new ramp. |
 |
30 June (wk 2) |
Metal-framed windows re-glazed. Red and yellow coloured glass replaced by blue. |
 |
23 June (wk 1) |
Windows stripped internally ready for re-glazing. Organ de-commissioned and sealed for protection. |
 |